High-strength, prefabricated, lightweight gauge steel truss system replaces termite-damaged roofs at scale
Across Valterra Platinum’s residential mining villages along the N11 corridor, termite infestation had caused widespread damage to the original timber roof structures. Over time, this had created an ongoing safety and maintenance risk, leaving families living beneath roofs they could no longer fully trust.
Mining operations in South Africa typically provide employee and community housing and they’re responsible for the maintenance and long-term habitability of that housing. This is the case for Valterra Plantinum’s mining villages.
They needed to develop a durable roofing solution that termites could not compromise again, that could be installed onto existing houses without overloading their walls and foundations, and that could be repeated across a large, phased refurbishment programme. Just as importantly, Valterra wanted the project to create local employment, build skills and deliver lasting value within the communities it serves.
Working with MiTek as the fabricator and Giant Engineering as the main structural engineer and roofing contractor, our lightweight gauge steel truss system, Ultra-Span, was chosen as the solution.
Why Ultra-Span?
MiTek’s Ultra-Span system offered a strong fit for the project. Manufactured from high-strength, thin-gauge galvanised steel, it’s not vulnerable to termite attack, rot or biological decay. This provided a permanent response to the issue that had undermined the original timber roofs.
Its low weight was equally important because the roof had to work as a retrofit system. At approximately 6–7kg/m², Ultra-Span could deliver the required structural performance while limiting the additional load transferred into the existing masonry walls and foundations. The trusses could also retain the familiar roof shape and concrete tile finish, allowing the homes to keep their established appearance while receiving a significant structural upgrade beneath the surface.
Engineering consistency through PAMIR
Although the houses were relatively simple in form, the challenge lay in delivering a consistent, code-compliant solution across properties of different ages, sizes and conditions.
MiTek’s PAMIR software was used to resolve the engineering before components reached site. Roof layouts, truss geometry, member sizing, bearing positions, bracing, connections and structural loading were all defined digitally. This allowed potential issues to be addressed early, reducing the need for interpretation, adjustment or redesign during installation.
As the programme progressed through different phases, PAMIR also allowed quantities and tonnages to be recalculated efficiently while maintaining the same engineering principles across the wider project. In practice, the complexity remained within the design and manufacturing process, leaving a clear and repeatable system for the teams working on site.
From controlled fabrication to local installation
Ultra-Span components were cut, punched, inspected and labelled at MiTek’s Midrand facility before being delivered to site with the relevant approved drawings. This installation-ready approach helped minimise cutting, waste and rework on site. This also suited the labour approach to this project.
Valterra Platinum were committed to making community involvement central to the project. Local people, many with no previous roofing experience, were recruited through traditional community leadership structures and trained to receive and sort deliveries, read layouts, assemble components and erect the trusses meeting compliance standards under Giant Engineering’s supervision. Over the four-year programme, these individuals developed into capable installation teams, able to deliver increasingly complex roofs safely and consistently.
The lightweight system made this possible. Components could be handled manually using simple tools, without cranes, heavy equipment or continuous electricity. Giant Engineering carried out regular inspections, while MiTek’s blue screws made it easier to confirm that the correct connections had been installed.
A durable, repeatable outcome
Each home within the first phase (186 roofs completed by the end of 2025) had to be refurbished within a fixed two-week rehousing window, making predictability essential. Pre-engineered kits, clear labelling and crane-free installation helped the teams work within this timeframe while reducing disruption to residents.
The result is a termite-resistant, fully engineered roof system that extends the life of the existing homes, reduces future maintenance risk and can be delivered consistently at scale.
The Valterra project shows that engineering innovation is not always about creating complex forms. Sometimes, its greatest value lies in developing a durable, repeatable solution that improves safety, protects existing assets and creates meaningful opportunities within the community. And Ultra-Span is helping to deliver just that.